Checklist for setting up industrial
units/enterprise in the State of Meghalaya (At the planning/pre-establishment stage)
Sl No | Particulars of document required | Whom to apply | Remark |
1. | State Single Window Agency’s clearance | Director of Commerce & Industries, Administrative Building, 2nd Floor, Lower Lachumiere, Shillong – 793 001 | Applicable for i) Any type of investment by Limited Company/Partnership firm/Non-local tribals
and which attracts provisions of the Meghalaya Transfer of Land (Regulation) Act, 1971
except (a) investment that is purely business in nature (b) cultivation and (c) Hydro-based power Plant and ii) Investment by a local tribal where the investment in Plant & Machinery /tools/equipments exceeds ₹25.00 lakh |
2. | Certificate of Incorporation | Registrar of Companies, Meghalaya etc., Morello Building, Shillong – 793 001 | Applicable for a Limited Company/One person Company/Limited Liability Partnership Firm http://www.mca.gov.in/MinistryV2/homepage.html |
3. | Firm’s Registration (i) For a Partnership firm (ii) For a Co-operative Society |
(i)Registrar of Firms, Administrative Building, 3rd Floor, Lower Lachumiere, Shillong – 793
001 (ii)Concerned Assistant Registrar of Co-operative Society in which the Society is located |
|
4. | NOC/Forest clearance | Concerned Divisional Forest Officer (Territorial) in which the Enterprise is located/Principal Chief Conservator of Forests & HOFF, Sylvan House, Lower Lachumiere, Shillong – 793 001 |
|
5. | (i) Environmental clearance for cement plant of 1.00 million tonnes per annum production capacity and above (ii) Environmental clearance for cement plant of less than 1.00 million tonnes per annum production capacity(iii) Environmental clearance for Thermal Power Plants of 500 MW or more (coal/lignite/naphta & gas based) and of 50 MW or more for Pet Coke Diesel and all other fuels(iv) Environmental clearance for Thermal Power Plants of 50 MW and above but less than 500 MW (coal/lignite/naphta & gas based) and of 5 MW or more but less than 50 MW for Pet coke diesel and all other fuels | (i) Ministry of Environment, Forests & Climate Change, Indira Paryavan Bhawan, Jorbagh Road, New Delhi – 110 003 (ii) Member Secretary, State Environment Impact Assessment Authority, Sylvan House, Lower Lachumiere, Shillong – 793 001(iii) Ministry of Environment, Forests & Climate Change, Indira Paryavan Bhawan, Jorbagh Road, New Delhi – 110 003(iv) Member Secretary, State Environment Impact Assessment Authority, Sylvan House, Lower Lachumiere, Shillong – 793 001 | Online application for environmental clearance may be submitted on the central portal https://parivesh.nic.in ----Online application for environmental clearance may be submitted on the central portal https://parivesh.nic.in ---- |
6. | Industrial Entrepreneur’s Memorandum (IEM) Part-A | Ministry of Commerce & Industry, Secretariat for Industrial Assistance, Public Relation & Complaints Section, Udyog Bhawan, New Delhi – 110 011 | Applicable for project where investment in Plant & Machinery exceeds 10 crore. It has to be applied through on-line mode only (www.eBiz.gov.in) |
7. | Trading License | Concerned Autonomous District Council (Khasi Hills Autonomous District Council/Jaintia Hills Autonomous District Council/Garo Hills Autonomous District Council) in which the Enterprise is located | ------ |
8. | “Consent to Establish” under the Water (Prevention & Control of Pollution) Act, 1974 and Air (Prevention & Control of Pollution) Act, 1981/“NOC” | Member Secretary, Meghalaya State Pollution Control Board, “ARDEN”, Lumpyngngad, Shillong – 793 014 | Applicable for Limited Company/Partnership Firm/Limited Liability Partnership Firm/firm owned by non-tribal |
9. | Building permission | Meghalaya Urban Development Authority, Police Bazar, Shillong – 793 001 | Applicable for units located in the Shillong Master Plan Areas and the Byrnihat Master Plan Scheme |
10. | Any other documents/NOC/clearance etc. that may be required by Central/State Government |